Created Methodology

This commit is contained in:
tripathyr 2021-10-27 06:59:23 +05:30 committed by GitHub
parent 49aede6e28
commit 1fee3a98b5
No known key found for this signature in database
GPG Key ID: 4AEE18F83AFDEB23

View File

@ -2,8 +2,8 @@
This is a pipeline of tasks that RanchiMall needs to get executed
# Execution Steps
As a start point, a project will be named as per the strategic requirements of RanchiMall
A team will be nominated that will work on that project. Those who do not perform well will drop off.
The team will conduct design discussions, and come up with two outputs: Design Document and list of tasks.
Design documents will be created on the project repository wiki page in GitHub itself
List of tasks will be uploaded in RIBC App for execution and monitoring
1. As a start point, a project will be named as per the strategic requirements of RanchiMall
2. A team will be nominated that will work on that project. Those who do not perform well will drop off.
3. The team will conduct design discussions, and come up with two outputs: Design Document and list of tasks.
4. Design documents will be created on the project repository wiki page in GitHub itself
5. List of tasks will be uploaded in RIBC App for execution and monitoring